Thursday, September 24, 2009

House: Second Week

Only a bit of progress on the house this week, several days were lost to miscellaneous tasks that had to happen in a specific order.

Last week they insulated the foundation.
DSC_3878

On Friday they hooked up sewer system and water pipes, which didn't make for interesting pictures. The foundation inspection on Monday didn't either.

Backfill on Tuesday made a big difference though.
DSC_3890

It was surprising how much of a difference the backfill made in terms of making the foundation look like a basement.
DSC_3893

Wednesday was lumber delivery
DSC_3896

According to the jobsite inventory list, there will be 508 2x4s delivered at some point. Right now it was mostly floor joists, flooring, beams. And fiber board, for some reason.
DSC_3915

Today the framing started, which should make for more dynamic progress next week.